Covalent Bonding, Structure and Shapes of Molecules – Topic 2A/B

£9.99

Covalent Bonding, Structure and Shapes of Molecules Topic 2A/2B

The Topic 2A/2B course on Edexcel A Level Chemistry provides approximately 14 hours of guided learning. Students work through three recorded video lessons, 94 marks of auto-marked MCQ practice, 180 marks of teacher-marked written questions, and a personalised spec-point progress report.

Guided Learning
14 Hours
total study time
Video Lessons
281 mins
3 recorded lessons
MCQ Assessments
94 Marks
5 quizzes
SAQ Assessments
180 Marks
6 quizzes

How the 14 guided learning hours are worked out

Guided learning hours are calculated from the actual contents of the course, not estimated. Video time is counted at its true running length, MCQs at 1.5 minutes per question, written answers at 1.5 minutes per mark, and time is allowed for reading the feedback returned on every quiz.

ComponentTime
Virtual lesson video281 min
MCQ practice (94 questions × 1.5 min)141 min
MCQ feedback review (5 quizzes × 10 min)50 min
SAQ practice (180 marks × 1.5 min)270 min
SAQ feedback review (6 quizzes × 15 min)90 min
Total832 min ≈ 14 hours

The three recorded lessons

The virtual lesson is delivered as three recorded lessons totalling 281 minutes. Students pause during exam-practice sections, attempt questions independently, then review the worked explanations and the mark-scheme approach.

LessonRunning time
1. Covalent Bonding78 min
2. Shapes of Molecules121 min
3. Exam Practice82 min
Total video281 min

Course preview

A short walkthrough of how the course is taught and how the assessment fits together.

At a glance

What you get in this course

281 minutes of guided video

Three recorded lessons covering Topic 2A and Topic 2A in full, with worked exam questions and mark-scheme strategy built into the teaching.

94 marks of MCQ practice

5 auto-marked quizzes of 17–21 questions each, with diagnostic feedback on every option. One attempt per quiz, so your scores track real progress.

180 marks of written practice

6 written-answer quizzes (78 questions) marked by a specialist chemistry teacher, assisted by KASP, with per-mark feedback returned the following Monday.

Complete spec-point coverage

36 Edexcel A level spec points are assessed in this course, every one of them in both question styles.

Exam-technique baked in

The lessons teach the chemistry and the exam wording. You learn what Edexcel actually rewards, not just the content.

Personalised progress report

A one-click PDF report shows your level on every spec point in colour-coded form.

What is KASP Analytics?

KASP (Knowledge Analytics & Spec-point Platform) tracks your progress at the level of individual specification points, not just whole quizzes. Every question on this course is mapped to the Edexcel A level spec point it assesses, so you always know exactly which parts of the specification you have mastered and which need another look.

Spec points tracked
36
Specification area
Topic 2A/2B: Bonding and Structure
Questions tagged
172
36 spec points assessed in this course

Bonding and Structure is split across two courses: this one covers covalent bonding, structure and molecular shapes, and the Ionic & Metallic course covers the rest. The intermolecular-forces spec points (2A.16 to 2A.21) belong to a separate topic. Across the 94 MCQ and 78 SAQ questions here, most of those spec points are assessed several times over, in both question styles.

Your topic dashboard

Every topic you have worked through is summarised here. At a glance you see how many questions you have attempted, what is still waiting to be marked, your total marks scored, and an overall score percentage. The dashboard below is an example, filled with the real topic structure of this course.

Hello, Sara – here is how you are doing

Edexcel A level Chemistry
TopicQuestions attemptedPendingMarks (scored / available)Score
Topic 2A: Covalent Bonding22 / 28436.00 / 50.0072%
Topic 2A: Shapes of Molecules19 / 26527.50 / 46.0060%

Spec-point breakdown for a topic

Click into any topic and you see the full spec-point breakdown. Each row is a single Edexcel A level spec point with its official wording, how many questions the bank holds against it, your score, and a colour that tells you immediately where to focus. The spec points and question counts below are the real ones from this course; the scores are an example.

Spec tagDescriptionAttemptedIn bankMarksScore
2A.8iibe able to draw dot-and-cross diagrams to show electrons in covalent substances, including: species exhibiting dative covalent (coordinate) bonding, including Al2Cl6 and ammonium ion4 / 4118.00 / 8.00100.0%
2A.10-aunderstand that the shape of a simple molecule is determined by repulsion between electron pairs around a central atom5 / 5109.00 / 11.0081.8%
2A.11-dunderstand reasons for the shape of, and bond angles in, NH33 / 3125.00 / 6.0083.3%
2A.11-eunderstand reasons for the shape of, and bond angles in, NH4+4 / 4106.00 / 9.0066.7%
2A.11-funderstand reasons for the shape of, and bond angles in, H2O5 / 5137.00 / 12.0058.3%
2A.15-bbe able to predict whether or not a given molecule is likely to be polar3 / 4234.00 / 8.0050.0%
2B.25-bknow the structure of diamond2 / 352.00 / 7.0028.6%
2B.25-cknow the structure of graphene0 / 35–Not yet attempted
■ Green 70–100%: secure mastery■ Orange 40–69%: some gaps■ Red 0–39%: needs attention■ Grey: not yet assessed

Printable progress report

One click and you can download a clean, branded Progress Report PDF for the topic. Useful for your own revision folder, for parents to see at a glance, or for tutors to plan focused sessions. Every spec point in the topic appears with its code and full requirement text, and the level column is colour-coded green through red.

A Level Chemistry progress report for Covalent Bonding, Structure and Shapes of Molecules showing student performance across specification points with colour coded levels for understanding
At a glance

What you get with KASP Analytics

Spec-point level tracking

Every question is tagged to the exact Edexcel A level spec point it assesses, so your scores roll up cleanly to the specification.

Updates automatically

Submit a quiz and your dashboard updates right away. Short-answer questions appear as pending until they have been marked.

Built for Edexcel A level

Wording, codes and topic structure follow the Edexcel A Level Chemistry specification exactly, so your scores line up with the document you will be examined on.

Printable report

One-click PDF Progress Report per topic, in the same colour system, ready for your folder or for a tutor session.

Both question styles counted

MCQ and written answers feed the same spec point. With 94 MCQ and 78 SAQ questions tagged, a weak area shows up whether you miss it under multiple choice or in writing.

Progress over time

A simple line chart shows how your overall score has trended across the days you have been studying.

What is the MCQ Bank?

The MCQ Bank for Topic 2A/2B is an auto-marked, instant-feedback practice engine built from past Edexcel A level paper questions. It runs to 5 quizzes, 94 questions and 94 marks. Every question is tagged to a specific Edexcel A level spec point, every option carries diagnostic feedback explaining the chemistry, and every quiz attempt feeds directly into your KASP Analytics dashboard.

Quizzes
5
Questions
94
Marks
94
Attempts
1 per quiz

Try a real Topic 2A/2B MCQ

This is a genuine question from the bank, reproduced exactly as it appears in the course. Click any option to reveal the diagnostic feedback for that choice, then expand the panel at the bottom for the full walkthrough.

Identifying the polar molecule

2A.15-b (Edexcel A level)1 mark

Which molecule is polar?

Click an option to see feedback

ANH3(g)
Correct

Correct. NH3 is pyramidal due to a lone pair on nitrogen. The N-H bond dipoles do not cancel and the lone pair contributes to the overall asymmetry, giving NH3 a permanent dipole moment.

BBeCl2(g)
Incorrect

Incorrect. Although BeCl2 has polar Be-Cl bonds, the molecule is linear. The two bond dipoles point in exactly opposite directions and cancel, so BeCl2 has no net dipole and is non-polar.

CSF6(g)
Incorrect

Incorrect. Although SF6 has six polar S-F bonds, the molecule is octahedral with perfect symmetry. The six bond dipoles cancel out in all directions, giving no net dipole. SF6 is non-polar.

DCO2(g)
Incorrect

Incorrect. Although CO2 has polar C=O bonds, the molecule is linear. The two bond dipoles point in exactly opposite directions and cancel out, so CO2 has no net dipole and is non-polar.

Show correct answer & full explanation →
General feedback

A molecule is polar if it has polar bonds and those bonds do not cancel out due to molecular symmetry. A lone pair on the central atom typically causes an asymmetric shape that results in a net dipole.

  • BeCl2(g): has two polar Be-Cl bonds, but the molecule is linear. The two dipoles point in exactly opposite directions and cancel, so BeCl2 is non-polar.
  • SF6(g): has six polar S-F bonds, but the molecule is octahedral with perfect symmetry. All six bond dipoles cancel, so SF6 is non-polar.
  • CO2(g): has two polar C=O bonds, but the molecule is linear. The dipoles point in opposite directions and cancel, so CO2 is non-polar.
  • NH3(g): has three polar N-H bonds and a lone pair on nitrogen, giving a pyramidal shape. The bond dipoles do not cancel, and the lone pair adds to the asymmetry. NH3 has a net dipole and is polar.

The correct answer is NH3(g).

5 quizzes, 94 marks of MCQ practice

The MCQ Bank is split across the two halves of the topic. Quizzes hold 17–21 questions worth one mark each, and each quiz is a single auto-marked attempt. Because every spec point is tested across several quizzes, your KASP scores reveal real improvement as you work through them.

Topic 2A: Covalent Bonding

3 quizzes · 52 marks
MCQ A
18
questions & marks
MCQ B
17
questions & marks
MCQ C
17
questions & marks

Topic 2A: Shapes of Molecules

2 quizzes · 42 marks
MCQ A
21
questions & marks
MCQ B
21
questions & marks
94 total marks94 questions in totalOne attempt per quizAuto-marked on submit
At a glance

What you get with the MCQ Bank

94 marks across 5 quizzes

3 quizzes on Covalent Bonding and 2 on Shapes of Molecules, 17–21 questions each, giving balanced coverage across the whole topic.

Instant auto-marking

Submit and the result is back in your hands inside a second. No waiting, no manual checking.

Diagnostic feedback per option

Every wrong option carries a tailored explanation of the misconception, not just a generic ‘incorrect’, plus a full walkthrough on every question.

Spec-point tagged

Each question is mapped to the Edexcel A level spec point it assesses, so your score flows straight into KASP Analytics.

Track improvement across quizzes

One attempt per quiz, but the same spec points appear across the set. Your scores from quiz to quiz show genuine progress, not repeat-attempt inflation.

Built from past papers

Every MCQ is sourced from genuine Edexcel A level past papers, with the wording polished for clarity and the chemistry verified.

What is the SAQ Bank?

The SAQ Bank for Topic 2A/2B is a written-answer practice engine marked by a specialist chemistry teacher, assisted by KASP. It runs to 6 quizzes, 78 questions and 180 marks. You attempt one quiz per week, submit your full written response, and your teacher returns mark-by-mark feedback the following Monday. Every comment is targeted at the exam wording you need to use.

Quizzes
6
Questions
78
Marks
180
Marks per quiz
30

A submitted SAQ and the feedback it gets

This is a genuine question from the bank with its real mark scheme. The submitted answer below is an example of a typical response at this standard. Expand the panel to see how it was marked.

Bond angles and shapes of water and the oxonium ion

2A.11-f (Edexcel A level)4 marks

Oxonium salts contain the oxonium ion, H3O+. This ion is formed when water forms a dative covalent bond with a proton.

Explain, using electron-pair repulsion theory, how the water molecule and the oxonium ion have different bond angles and shapes.

Submitted answer

In water the oxygen atom has two bonding pairs and two lone pairs, which makes the molecule bent with a bond angle of 104.5°. In the oxonium ion the oxygen has three bonding pairs and one lone pair, so it is trigonal pyramidal with a bond angle of 107°.

View returned feedback →
Returned by your chemistry specialist3 / 4 · 75%
Mark scheme
Criterion
✓Bond angles: 104.5 degrees in water and 107 degrees in the oxonium ion.
Awarded – both angles quoted correctly, and to the precision the mark scheme expects.
✓Shapes: bent / V-shaped for water and (trigonal) pyramidal for the oxonium ion.
Awarded – both shapes named correctly.
✓Water has two bonded pairs (of electrons) plus two lone pairs and the oxonium ion has three bonded pairs plus one lone pair.
Awarded – the electron-pair counts are right for both species.
✗Lone pairs repel more (than bonded pairs, and water has more lone pairs, so the bond angle is smaller in water / the shape changes).
Not awarded. You gave the shapes and the angles but never said why they differ. The mark needs the repulsion argument: lone pairs repel more strongly than bonding pairs, and water has two lone pairs to the oxonium ion's one, so the bond angle in water is squeezed further.
Teacher comment

Three marks banked cleanly, Sara – the shapes, the angles and the electron-pair counts are all correct, which is more than most students manage on this question. The mark you have missed is the one the question is really testing: it says ‘using electron-pair repulsion theory’, so the examiner wants the comparison, not just the description. Add one sentence – lone pairs repel more than bonding pairs, and water has an extra lone pair, so its angle is smaller – and this is a full-mark answer.

A predictable weekly rhythm over 6 weeks

One quiz per week across the 6 quizzes, so the SAQ Bank runs as a 6-week programme. Submit anywhere from Monday to Friday, marking happens over the weekend, and you receive your feedback by the following Monday. The rhythm is the same every week so you always know when to expect a return.

Mon
Submit
Tue
Submit
Wed
Submit
Thu
Submit
Fri
Submit
Sat
Marking
Sun
Marking
Mon
Returned

One attempt per quiz, one quiz submitted per week. Because the same spec points reappear across the 6 quizzes, your scores over the programme show genuine improvement – not repeat-attempt inflation. The weekly cap also keeps the marking load manageable so your feedback stays genuinely thorough.

6 quizzes, 180 marks of written practice

The SAQ Bank holds 78 questions and 180 marks between its 6 quizzes. Every quiz is worth 30 marks, and runs to between 11 and 16 questions depending on how the marks fall, with the parts of any one original exam question kept together in the same quiz. They draw from past Edexcel A level written-paper questions across the whole topic pair.

Topic 2A: Covalent Bonding

3 quizzes · 90 marks
SAQ A
30
marks · 14 questions
SAQ B
30
marks · 14 questions
SAQ C
30
marks · 16 questions

Topic 2A: Shapes of Molecules

3 quizzes · 90 marks
SAQ A
30
marks · 12 questions
SAQ B
30
marks · 11 questions
SAQ C
30
marks · 11 questions
180 total marks78 questions1 quiz per week, over 6 weeksReturned the following Monday

What the written questions ask you to do

The bank is not all prose. Alongside written explanations you are asked to draw structures and mechanisms and to work through calculations, all marked by a specialist chemistry teacher, assisted by KASP, against the same mark scheme.

Question styleQuestionsWhat it asks for
Written answer57Explanations, descriptions, equations and definitions, marked against the exam mark scheme point by point.
Drawing21Structural and displayed formulae, skeletal structures and mechanism steps, drawn on screen and marked by your teacher, assisted by KASP.
Total78
At a glance

What you get with the SAQ Bank

180 marks across 6 quizzes

3 quizzes on Covalent Bonding and 3 on Shapes of Molecules, holding 78 questions between them at 30 marks per quiz.

Marked by a teacher, assisted by KASP

KASP drafts the marking; your teacher reads your answer end to end, decides every mark and writes the comments.

Per-mark feedback

Every mark in the scheme is checked off explicitly. You see exactly which marks you earned and what wording the missed ones needed.

Predictable weekly turnaround

Submit by Friday, marked over the weekend, feedback returned by Monday. One quiz per week; one attempt per quiz; 6 weeks end to end.

Exam-board wording focus

Feedback teaches the precise language the Edexcel mark scheme rewards, so the next time the topic appears you write to score.

Feeds your KASP dashboard

Every SAQ is spec-point tagged. Once marked, your scores flow into KASP Analytics alongside your MCQ results.

Exam Board Alignment

Covalent Bonding, Structure & Shapes of Molecules Topic 2A/B Edexcel A Level Chemistry

This course covers the following Edexcel A Level Chemistry specification points. These are limited to covalent bonding, covalent structure, VSEPR theory and molecular shapes.

7
know that a covalent bond is the strong electrostatic attraction between two nuclei and the shared pair of electrons between them
8
be able to draw dot-and-cross diagrams to show electrons in covalent substances, including:
i
molecules with single, double and triple bonds
ii
species exhibiting dative covalent (coordinate) bonding, including Al2Cl6 and ammonium ion
9
understand the relationship between bond lengths and bond strengths for covalent bonds
10
understand that the shape of a simple molecule or ion is determined by the repulsion between the electron pairs that surround a central atom
11
understand reasons for the shapes of, and bond angles in, simple molecules and ions with up to six outer pairs of electrons, including any combination of bonding pairs and lone pairs
Examples should include BeCl2, BCl3, CH4, NH3, NH4+, H2O, CO2, PCl5(g), SF6(g) and related molecules and ions, as well as simple organic molecules in this specification.
12
be able to predict the shapes of, and bond angles in, simple molecules and ions analogous to those specified above using electron-pair repulsion theory
13
know that electronegativity is the ability of an atom to attract the bonding electrons in a covalent bond
14
know that ionic and covalent bonding are the extremes of a continuum of bonding type and that electronegativity differences lead to bond polarity in bonds and molecules
15
understand that molecules with polar bonds may not be polar molecules and be able to predict whether or not a given molecule is likely to be polar
23
know that giant lattices are present in:
ii
covalently bonded solids, such as diamond, graphite and silicon(IV) oxide (giant covalent lattices)
24
know that the structure of covalently bonded substances such as iodine, I2, and ice, H2O, is simple molecular
25
know the different structures formed by carbon atoms, including graphite, diamond and graphene
26
be able to predict the type of structure and bonding present in a substance from numerical data and/or other information
27
be able to predict the physical properties of a substance, including melting and boiling temperature, electrical conductivity and solubility in water, in terms of:
i
the types of particle present, including atoms and molecules where relevant
ii
the structure of the substance
iii
the type of bonding and the presence of intermolecular forces, where relevant
Specification Coverage

Students will be assessed on their ability to:

The following specification points are limited to covalent bonding, covalent structure, VSEPR theory and molecular shapes.

7
know that a covalent bond is the strong electrostatic attraction between two nuclei and the shared pair of electrons between them
8
be able to draw dot-and-cross diagrams to show electrons in covalent substances, including:
i
molecules with single, double and triple bonds
ii
species exhibiting dative covalent (coordinate) bonding, including Al2Cl6 and ammonium ion
9
understand the relationship between bond lengths and bond strengths for covalent bonds
10
understand that the shape of a simple molecule or ion is determined by the repulsion between the electron pairs that surround a central atom
11
understand reasons for the shapes of, and bond angles in, simple molecules and ions with up to six outer pairs of electrons, including any combination of bonding pairs and lone pairs
Examples should include BeCl2, BCl3, CH4, NH3, NH4+, H2O, CO2, PCl5(g), SF6(g) and related molecules and ions, as well as simple organic molecules in this specification.
12
be able to predict the shapes of, and bond angles in, simple molecules and ions analogous to those specified above using electron-pair repulsion theory
13
know that electronegativity is the ability of an atom to attract the bonding electrons in a covalent bond
14
know that ionic and covalent bonding are the extremes of a continuum of bonding type and that electronegativity differences lead to bond polarity in bonds and molecules
15
understand that molecules with polar bonds may not be polar molecules and be able to predict whether or not a given molecule is likely to be polar
23
know that giant lattices are present in:
ii
covalently bonded solids, such as diamond, graphite and silicon(IV) oxide (giant covalent lattices)
24
know that the structure of covalently bonded substances such as iodine, I2, and ice, H2O, is simple molecular
25
know the different structures formed by carbon atoms, including graphite, diamond and graphene
26
be able to predict the type of structure and bonding present in a substance from numerical data and/or other information
27
be able to predict the physical properties of a substance, including melting and boiling temperature, electrical conductivity and solubility in water, in terms of:
i
the types of particle present, including atoms and molecules where relevant
ii
the structure of the substance
iii
the type of bonding and the presence of intermolecular forces, where relevant
Complete Topic Package

Learn the content, practise exam questions, and identify exactly where marks are being lost.

This course combines guided video teaching, diagnostic MCQs, teacher-marked written assessment, and detailed specification reporting for Edexcel A Level Chemistry.

Exam-focused learning with clear performance feedback